Safety-stock recommendations

Every number is explained — demand variability, lead time, vendor reliability, equipment criticality and network cover.

Reduce
177
Retain
17
Increase
50
Capital release
₹3.24 Cr
reduce
Criticality A
1020100593 · Chennai

GEARBOX R60DRN90 | SEW | Helical Geared Motor 1.5kW 45rpm Var-2

Reduce safety stock for SEW R60DRN90 at Chennai from 28 to 10 EA. Demand at Chennai averages 4.2 EA/month (variable profile, std dev 2.3). Lead time is 55 days from SEW Eurodrive India (OTIF 93.2%). An additional 67 equivalent units are available across other plants.

Safety stock
28 → 10
₹19.05 Lakh released
On hand
41 EA
Avg demand
4.25/mo
Std dev
2.35
Lead time
55 d
Service factor
2.05
Network cover
67 EA
  • Demand at Chennai averages 4.2 EA/month (variable profile, std dev 2.3).
  • Lead time is 55 days from SEW Eurodrive India (OTIF 93.2%).
  • Equipment criticality A on Biscuit Line 3 - Main Drive (downtime ₹287,444/hr) sets a 2.04 service factor.
  • 67 equivalent units are available at other plants and can be transferred in days, not weeks.
retain
Criticality A
1030100629 · Kolkata

GEARBOX R59DRN90 | SEW | Helical Geared Motor 1.5kW 45rpm Var-3

Retain safety stock for SEW R59DRN90 at Kolkata from 1 to 1 EA. No consumption recorded in the last 12 months at this location, so cover is held only as an insurance position. Demand at Kolkata averages 0.0 EA/month (lumpy profile, std dev 0.0). An additional 41 equivalent units are available across other plants.

Safety stock
1 → 1
On hand
22 EA
Avg demand
0/mo
Std dev
0
Lead time
38 d
Service factor
2.05
Network cover
41 EA
  • No consumption recorded in the last 12 months at this location, so cover is held only as an insurance position.
  • Demand at Kolkata averages 0.0 EA/month (lumpy profile, std dev 0.0).
  • Lead time is 38 days from SEW Eurodrive India (OTIF 90.1%).
  • Equipment criticality A on Biscuit Line 3 - Main Drive (downtime ₹353,404/hr) sets a 2.04 service factor.
  • 41 equivalent units are available at other plants and can be transferred in days, not weeks.
  • No goods movement for 24 months — carrying risk outweighs stock-out risk.
increase
Criticality A
1040100633 · Hajipur

GEARBOX R59DRN90 | SEW | Helical Geared Motor 1.5kW 45rpm Var-3

Increase safety stock for SEW R59DRN90 at Hajipur from 2 to 3 EA. Demand at Hajipur averages 0.3 EA/month (lumpy profile, std dev 1.1). Lead time is 33 days from SEW Eurodrive India (OTIF 70.2%). An additional 38 equivalent units are available across other plants.

Safety stock
2 → 3
On hand
25 EA
Avg demand
0.33/mo
Std dev
1.11
Lead time
33 d
Service factor
2.05
Network cover
38 EA
  • Demand at Hajipur averages 0.3 EA/month (lumpy profile, std dev 1.1).
  • Lead time is 33 days from SEW Eurodrive India (OTIF 70.2%).
  • Equipment criticality A on Biscuit Line 3 - Main Drive (downtime ₹239,914/hr) sets a 2.04 service factor.
  • 38 equivalent units are available at other plants and can be transferred in days, not weeks.
  • No goods movement for 24 months — carrying risk outweighs stock-out risk.
reduce
Criticality A
1010100592 · Ranjangaon

GEARBOX R60DRN90 | SEW | Helical Geared Motor 1.5kW 45rpm Var-2

Reduce safety stock for SEW R60DRN90 at Ranjangaon from 28 to 11 EA. Demand at Ranjangaon averages 4.9 EA/month (variable profile, std dev 2.6). Lead time is 55 days from SEW Eurodrive India (OTIF 85.5%). An additional 73 equivalent units are available across other plants.

Safety stock
28 → 11
₹18.35 Lakh released
On hand
35 EA
Avg demand
4.92/mo
Std dev
2.56
Lead time
55 d
Service factor
2.05
Network cover
73 EA
  • Demand at Ranjangaon averages 4.9 EA/month (variable profile, std dev 2.6).
  • Lead time is 55 days from SEW Eurodrive India (OTIF 85.5%).
  • Equipment criticality A on Biscuit Line 3 - Main Drive (downtime ₹254,880/hr) sets a 2.04 service factor.
  • 73 equivalent units are available at other plants and can be transferred in days, not weeks.
  • No goods movement for 24 months — carrying risk outweighs stock-out risk.
reduce
Criticality C
1010101369 · Ranjangaon

VALVE VUVG-L16 | Festo | Solenoid Valve 5/2 24VDC G1/8 Var-2

Reduce safety stock for Festo VUVG-L16 at Ranjangaon from 95 to 8 EA. Demand at Ranjangaon averages 12.6 EA/month (variable profile, std dev 5.2). Lead time is 30 days from Festo India (OTIF 95.7%). An additional 270 equivalent units are available across other plants.

Safety stock
95 → 8
₹9.11 Lakh released
On hand
121 EA
Avg demand
12.58/mo
Std dev
5.17
Lead time
30 d
Service factor
1.28
Network cover
270 EA
  • Demand at Ranjangaon averages 12.6 EA/month (variable profile, std dev 5.2).
  • Lead time is 30 days from Festo India (OTIF 95.7%).
  • Equipment criticality C on Packaging Line 4 - Pick&Place (downtime ₹33,101/hr) sets a 1.28 service factor.
  • 270 equivalent units are available at other plants and can be transferred in days, not weeks.
reduce
Criticality B
1030102370 · Kolkata

PUMP CM6-4-A | Grundfos | Centrifugal Pump 0.75kW SS Var-2

Reduce safety stock for Grundfos CM6-4-A at Kolkata from 45 to 5 EA. Demand at Kolkata averages 5.0 EA/month (variable profile, std dev 2.5). Lead time is 32 days from Grundfos Pumps India (OTIF 66.1%). An additional 19 equivalent units are available across other plants.

Safety stock
45 → 5
₹10.06 Lakh released
On hand
49 EA
Avg demand
5/mo
Std dev
2.55
Lead time
32 d
Service factor
1.64
Network cover
19 EA
  • Demand at Kolkata averages 5.0 EA/month (variable profile, std dev 2.5).
  • Lead time is 32 days from Grundfos Pumps India (OTIF 66.1%).
  • Equipment criticality B on CIP Skid - Supply Pump (downtime ₹99,467/hr) sets a 1.64 service factor.
  • 19 equivalent units are available at other plants and can be transferred in days, not weeks.
reduce
Criticality A
1040100557 · Hajipur

GEARBOX R57DRN90 | SEW | Helical Geared Motor 1.5kW 45rpm

Reduce safety stock for SEW R57DRN90 at Hajipur from 15 to 2 EA. Demand at Hajipur averages 2.2 EA/month (stable profile, std dev 0.4). Lead time is 42 days from SEW Eurodrive India (OTIF 62.4%). An additional 24 equivalent units are available across other plants.

Safety stock
15 → 2
₹9.14 Lakh released
On hand
19 EA
Avg demand
2.25/mo
Std dev
0.43
Lead time
42 d
Service factor
2.05
Network cover
24 EA
  • Demand at Hajipur averages 2.2 EA/month (stable profile, std dev 0.4).
  • Lead time is 42 days from SEW Eurodrive India (OTIF 62.4%).
  • Equipment criticality A on Biscuit Line 3 - Main Drive (downtime ₹195,765/hr) sets a 2.04 service factor.
  • 24 equivalent units are available at other plants and can be transferred in days, not weeks.
reduce
Criticality C
1020101815 · Chennai

COUPLING L-101-14 | Lovejoy | Jaw Coupling L100 Bore 14mm Var-2

Reduce safety stock for Lovejoy L-101-14 at Chennai from 510 to 18 EA. Demand at Chennai averages 60.4 EA/month (variable profile, std dev 20.3). Lead time is 13 days from Lovejoy India (OTIF 91.7%). An additional 428 equivalent units are available across other plants.

Safety stock
510 → 18
₹7.36 Lakh released
On hand
678 EA
Avg demand
60.42/mo
Std dev
20.27
Lead time
13 d
Service factor
1.28
Network cover
428 EA
  • Demand at Chennai averages 60.4 EA/month (variable profile, std dev 20.3).
  • Lead time is 13 days from Lovejoy India (OTIF 91.7%).
  • Equipment criticality C on Utility - Water Pump (downtime ₹29,144/hr) sets a 1.28 service factor.
  • 428 equivalent units are available at other plants and can be transferred in days, not weeks.
reduce
Criticality C
1050100148 · Bidadi

BEARING 22219 | SKF | Spherical Roller Bearing 80x140x33mm Var-2

Reduce safety stock for SKF 22219 at Bidadi from 135 to 8 EA. Demand at Bidadi averages 16.4 EA/month (variable profile, std dev 6.0). Lead time is 21 days from SKF India Ltd (OTIF 69.7%). An additional 295 equivalent units are available across other plants.

Safety stock
135 → 8
₹7.17 Lakh released
On hand
183 EA
Avg demand
16.42/mo
Std dev
6.05
Lead time
21 d
Service factor
1.28
Network cover
295 EA
  • Demand at Bidadi averages 16.4 EA/month (variable profile, std dev 6.0).
  • Lead time is 21 days from SKF India Ltd (OTIF 69.7%).
  • Equipment criticality C on Flour Handling - Sifter Drive (downtime ₹12,292/hr) sets a 1.28 service factor.
  • 295 equivalent units are available at other plants and can be transferred in days, not weeks.
  • No goods movement for 13 months — carrying risk outweighs stock-out risk.
retain
Criticality C
1040100853 · Hajipur

MOTOR 3LE7-100L | Siemens | 3PH IE3 Motor 2.2kW 1440rpm Var-3

Retain safety stock for Siemens 3LE7-100L at Hajipur from 1 to 1 EA. Demand at Hajipur averages 0.4 EA/month (lumpy profile, std dev 1.0). Lead time is 44 days from Siemens Ltd (OTIF 78.9%). An additional 42 equivalent units are available across other plants.

Safety stock
1 → 1
On hand
24 EA
Avg demand
0.42/mo
Std dev
0.95
Lead time
44 d
Service factor
1.28
Network cover
42 EA
  • Demand at Hajipur averages 0.4 EA/month (lumpy profile, std dev 1.0).
  • Lead time is 44 days from Siemens Ltd (OTIF 78.9%).
  • Equipment criticality C on Utility - Air Compressor (downtime ₹36,992/hr) sets a 1.28 service factor.
  • 42 equivalent units are available at other plants and can be transferred in days, not weeks.
  • No goods movement for 31 months — carrying risk outweighs stock-out risk.
reduce
Criticality B
1040101925 · Hajipur

CHAIN SS-883-TAB | Rexnord | Table Top Chain SS 88.9mm Var-2

Reduce safety stock for Rexnord SS-883-TAB at Hajipur from 110 to 20 M. Demand at Hajipur averages 16.5 M/month (variable profile, std dev 8.3). Lead time is 29 days from Rexnord India (OTIF 84.1%). An additional 7 equivalent units are available across other plants.

Safety stock
110 → 20
₹7.09 Lakh released
On hand
147 M
Avg demand
16.5/mo
Std dev
8.33
Lead time
29 d
Service factor
1.64
Network cover
7 M
  • Demand at Hajipur averages 16.5 M/month (variable profile, std dev 8.3).
  • Lead time is 29 days from Rexnord India (OTIF 84.1%).
  • Equipment criticality B on Packaging Line 3 - Infeed (downtime ₹65,644/hr) sets a 1.64 service factor.
  • 7 equivalent units are available at other plants and can be transferred in days, not weeks.
reduce
Criticality A
1030100594 · Kolkata

GEARBOX R60DRN90 | SEW | Helical Geared Motor 1.5kW 45rpm Var-2

Reduce safety stock for SEW R60DRN90 at Kolkata from 18 to 10 EA. Demand at Kolkata averages 3.8 EA/month (variable profile, std dev 1.6). Lead time is 47 days from SEW Eurodrive India (OTIF 95.5%). An additional 88 equivalent units are available across other plants.

Safety stock
18 → 10
₹8.44 Lakh released
On hand
20 EA
Avg demand
3.75/mo
Std dev
1.59
Lead time
47 d
Service factor
2.05
Network cover
88 EA
  • Demand at Kolkata averages 3.8 EA/month (variable profile, std dev 1.6).
  • Lead time is 47 days from SEW Eurodrive India (OTIF 95.5%).
  • Equipment criticality A on Biscuit Line 3 - Main Drive (downtime ₹297,787/hr) sets a 2.04 service factor.
  • 88 equivalent units are available at other plants and can be transferred in days, not weeks.
reduce
Criticality B
1040100260 · Hajipur

BEARING 6309 | FAG | Deep Groove Ball Bearing 40x90x23mm Var-2

Reduce safety stock for FAG 6309 at Hajipur from 389 to 24 EA. Demand at Hajipur averages 53.8 EA/month (variable profile, std dev 28.3). Lead time is 9 days from Schaeffler India (OTIF 77.2%). An additional 919 equivalent units are available across other plants.

Safety stock
389 → 24
₹6.40 Lakh released
On hand
539 EA
Avg demand
53.75/mo
Std dev
28.26
Lead time
9 d
Service factor
1.64
Network cover
919 EA
  • Demand at Hajipur averages 53.8 EA/month (variable profile, std dev 28.3).
  • Lead time is 9 days from Schaeffler India (OTIF 77.2%).
  • Equipment criticality B on Packaging Line 4 - Wrapper (downtime ₹88,186/hr) sets a 1.64 service factor.
  • 919 equivalent units are available at other plants and can be transferred in days, not weeks.
reduce
Criticality C
1010101706 · Ranjangaon

SENSOR IFS205 | IFM | Inductive Proximity Sensor M12 PNP Var-2

Reduce safety stock for IFM IFS205 at Ranjangaon from 108 to 8 EA. Demand at Ranjangaon averages 15.4 EA/month (variable profile, std dev 6.2). Lead time is 19 days from IFM Electronic India (OTIF 63.7%). An additional 180 equivalent units are available across other plants.

Safety stock
108 → 8
₹6.19 Lakh released
On hand
150 EA
Avg demand
15.42/mo
Std dev
6.16
Lead time
19 d
Service factor
1.28
Network cover
180 EA
  • Demand at Ranjangaon averages 15.4 EA/month (variable profile, std dev 6.2).
  • Lead time is 19 days from IFM Electronic India (OTIF 63.7%).
  • Equipment criticality C on Cake Line 2 - Indexer (downtime ₹36,529/hr) sets a 1.28 service factor.
  • 180 equivalent units are available at other plants and can be transferred in days, not weeks.
reduce
Criticality C
1040100149 · Hajipur

BEARING 22219 | SKF | Spherical Roller Bearing 80x140x33mm Var-2

Reduce safety stock for SKF 22219 at Hajipur from 139 to 9 EA. Demand at Hajipur averages 18.2 EA/month (variable profile, std dev 7.9). Lead time is 21 days from SKF India Ltd (OTIF 92.7%). An additional 309 equivalent units are available across other plants.

Safety stock
139 → 9
₹7.11 Lakh released
On hand
169 EA
Avg demand
18.25/mo
Std dev
7.89
Lead time
21 d
Service factor
1.28
Network cover
309 EA
  • Demand at Hajipur averages 18.2 EA/month (variable profile, std dev 7.9).
  • Lead time is 21 days from SKF India Ltd (OTIF 92.7%).
  • Equipment criticality C on Flour Handling - Sifter Drive (downtime ₹31,156/hr) sets a 1.28 service factor.
  • 309 equivalent units are available at other plants and can be transferred in days, not weeks.
increase
Criticality A
1010100520 · Ranjangaon

GEARBOX VF55-P80 | Bonfiglioli | Worm Gearbox Ratio 30:1 0.75kW Var-3

Increase safety stock for Bonfiglioli VF55-P80 at Ranjangaon from 1 to 3 EA. Demand at Ranjangaon averages 0.3 EA/month (lumpy profile, std dev 1.1). Lead time is 34 days from Bonfiglioli Transmissions (OTIF 97.4%). An additional 23 equivalent units are available across other plants.

Safety stock
1 → 3
On hand
13 EA
Avg demand
0.33/mo
Std dev
1.11
Lead time
34 d
Service factor
2.05
Network cover
23 EA
  • Demand at Ranjangaon averages 0.3 EA/month (lumpy profile, std dev 1.1).
  • Lead time is 34 days from Bonfiglioli Transmissions (OTIF 97.4%).
  • Equipment criticality A on Cake Line 1 - Depositor (downtime ₹331,279/hr) sets a 2.04 service factor.
  • 23 equivalent units are available at other plants and can be transferred in days, not weeks.
  • No goods movement for 15 months — carrying risk outweighs stock-out risk.
reduce
Criticality B
1050101036 · Bidadi

SEAL MS-2101 | Garlock | Mechanical Shaft Seal 25mm SiC Var-2

Reduce safety stock for Garlock MS-2101 at Bidadi from 70 to 9 EA. Demand at Bidadi averages 12.4 EA/month (variable profile, std dev 5.0). Lead time is 25 days from Garlock India (OTIF 66.9%). An additional 38 equivalent units are available across other plants.

Safety stock
70 → 9
₹7.10 Lakh released
On hand
85 EA
Avg demand
12.42/mo
Std dev
4.96
Lead time
25 d
Service factor
1.64
Network cover
38 EA
  • Demand at Bidadi averages 12.4 EA/month (variable profile, std dev 5.0).
  • Lead time is 25 days from Garlock India (OTIF 66.9%).
  • Equipment criticality B on CIP Skid - Transfer Pump (downtime ₹104,873/hr) sets a 1.64 service factor.
  • 38 equivalent units are available at other plants and can be transferred in days, not weeks.
reduce
Criticality C
1020101371 · Chennai

VALVE VUVG-L16 | Festo | Solenoid Valve 5/2 24VDC G1/8 Var-2

Reduce safety stock for Festo VUVG-L16 at Chennai from 72 to 6 EA. Demand at Chennai averages 8.8 EA/month (variable profile, std dev 3.3). Lead time is 27 days from Festo India (OTIF 66.1%). An additional 307 equivalent units are available across other plants.

Safety stock
72 → 6
₹6.62 Lakh released
On hand
84 EA
Avg demand
8.83/mo
Std dev
3.31
Lead time
27 d
Service factor
1.28
Network cover
307 EA
  • Demand at Chennai averages 8.8 EA/month (variable profile, std dev 3.3).
  • Lead time is 27 days from Festo India (OTIF 66.1%).
  • Equipment criticality C on Packaging Line 4 - Pick&Place (downtime ₹44,090/hr) sets a 1.28 service factor.
  • 307 equivalent units are available at other plants and can be transferred in days, not weeks.
reduce
Criticality C
1030101705 · Kolkata

SENSOR IFS205 | IFM | Inductive Proximity Sensor M12 PNP Var-2

Reduce safety stock for IFM IFS205 at Kolkata from 87 to 7 EA. Demand at Kolkata averages 13.8 EA/month (variable profile, std dev 5.5). Lead time is 22 days from IFM Electronic India (OTIF 96.6%). An additional 207 equivalent units are available across other plants.

Safety stock
87 → 7
₹4.93 Lakh released
On hand
123 EA
Avg demand
13.83/mo
Std dev
5.51
Lead time
22 d
Service factor
1.28
Network cover
207 EA
  • Demand at Kolkata averages 13.8 EA/month (variable profile, std dev 5.5).
  • Lead time is 22 days from IFM Electronic India (OTIF 96.6%).
  • Equipment criticality C on Cake Line 2 - Indexer (downtime ₹33,275/hr) sets a 1.28 service factor.
  • 207 equivalent units are available at other plants and can be transferred in days, not weeks.
reduce
Criticality C
1030100372 · Kolkata

BEARING UC212 | NBC | Pillow Block Insert Bearing 45mm Var-2

Reduce safety stock for NBC UC212 at Kolkata from 277 to 14 EA. Demand at Kolkata averages 35.5 EA/month (variable profile, std dev 16.7). Lead time is 14 days from NEI Jaipur (OTIF 92.4%). An additional 599 equivalent units are available across other plants.

Safety stock
277 → 14
₹4.87 Lakh released
On hand
378 EA
Avg demand
35.5/mo
Std dev
16.72
Lead time
14 d
Service factor
1.28
Network cover
599 EA
  • Demand at Kolkata averages 35.5 EA/month (variable profile, std dev 16.7).
  • Lead time is 14 days from NEI Jaipur (OTIF 92.4%).
  • Equipment criticality C on Utility - Cooling Tower Fan (downtime ₹31,531/hr) sets a 1.28 service factor.
  • 599 equivalent units are available at other plants and can be transferred in days, not weeks.
reduce
Criticality B
1010101225 · Ranjangaon

BELT NAT-15EIC | Habasit | Modular Conveyor Belt 15mm Pitch

Reduce safety stock for Habasit NAT-15EIC at Ranjangaon from 34 to 4 M. Demand at Ranjangaon averages 7.7 M/month (stable profile, std dev 0.6). Lead time is 50 days from Habasit Iakoka (OTIF 87.4%). An additional 115 equivalent units are available across other plants.

Safety stock
34 → 4
₹3.84 Lakh released
On hand
58 M
Avg demand
7.67/mo
Std dev
0.62
Lead time
50 d
Service factor
1.64
Network cover
115 M
  • Demand at Ranjangaon averages 7.7 M/month (stable profile, std dev 0.6).
  • Lead time is 50 days from Habasit Iakoka (OTIF 87.4%).
  • Equipment criticality B on Biscuit Line 2 - Cooling Conveyor (downtime ₹69,911/hr) sets a 1.64 service factor.
  • 115 equivalent units are available at other plants and can be transferred in days, not weeks.
reduce
Criticality A
1030100521 · Kolkata

GEARBOX VF55-P80 | Bonfiglioli | Worm Gearbox Ratio 30:1 0.75kW Var-3

Reduce safety stock for Bonfiglioli VF55-P80 at Kolkata from 12 to 6 EA. Demand at Kolkata averages 1.3 EA/month (lumpy profile, std dev 1.9). Lead time is 34 days from Bonfiglioli Transmissions (OTIF 68.7%). An additional 21 equivalent units are available across other plants.

Safety stock
12 → 6
₹5.04 Lakh released
On hand
15 EA
Avg demand
1.33/mo
Std dev
1.93
Lead time
34 d
Service factor
2.05
Network cover
21 EA
  • Demand at Kolkata averages 1.3 EA/month (lumpy profile, std dev 1.9).
  • Lead time is 34 days from Bonfiglioli Transmissions (OTIF 68.7%).
  • Equipment criticality A on Cake Line 1 - Depositor (downtime ₹199,856/hr) sets a 2.04 service factor.
  • 21 equivalent units are available at other plants and can be transferred in days, not weeks.
reduce
Criticality C
1020100150 · Chennai

BEARING 22219 | SKF | Spherical Roller Bearing 80x140x33mm Var-2

Reduce safety stock for SKF 22219 at Chennai from 88 to 5 EA. Demand at Chennai averages 11.4 EA/month (variable profile, std dev 3.4). Lead time is 23 days from SKF India Ltd (OTIF 91.1%). An additional 352 equivalent units are available across other plants.

Safety stock
88 → 5
₹4.44 Lakh released
On hand
126 EA
Avg demand
11.42/mo
Std dev
3.38
Lead time
23 d
Service factor
1.28
Network cover
352 EA
  • Demand at Chennai averages 11.4 EA/month (variable profile, std dev 3.4).
  • Lead time is 23 days from SKF India Ltd (OTIF 91.1%).
  • Equipment criticality C on Flour Handling - Sifter Drive (downtime ₹40,847/hr) sets a 1.28 service factor.
  • 352 equivalent units are available at other plants and can be transferred in days, not weeks.
increase
Criticality A
1010102333 · Ranjangaon

PUMP CM3-4-A | Grundfos | Centrifugal Pump 0.75kW SS

Increase safety stock for Grundfos CM3-4-A at Ranjangaon from 2 to 5 EA. Demand at Ranjangaon averages 2.4 EA/month (stable profile, std dev 0.6). Lead time is 40 days from Grundfos Pumps India (OTIF 90.5%). An additional 30 equivalent units are available across other plants.

Safety stock
2 → 5
On hand
25 EA
Avg demand
2.42/mo
Std dev
0.64
Lead time
40 d
Service factor
2.05
Network cover
30 EA
  • Demand at Ranjangaon averages 2.4 EA/month (stable profile, std dev 0.6).
  • Lead time is 40 days from Grundfos Pumps India (OTIF 90.5%).
  • Equipment criticality A on CIP Skid - Supply Pump (downtime ₹185,917/hr) sets a 2.04 service factor.
  • 30 equivalent units are available at other plants and can be transferred in days, not weeks.
  • No goods movement for 24 months — carrying risk outweighs stock-out risk.
reduce
Criticality A
1010101480 · Ranjangaon

VALVE LKB-54 | Alfa Laval | Sanitary Butterfly Valve DN51 SS316 Var-2

Reduce safety stock for Alfa Laval LKB-54 at Ranjangaon from 79 to 18 EA. Demand at Ranjangaon averages 10.2 EA/month (variable profile, std dev 7.1). Lead time is 30 days from Alfa Laval India (OTIF 96.8%). An additional 38 equivalent units are available across other plants.

Safety stock
79 → 18
₹4.80 Lakh released
On hand
102 EA
Avg demand
10.17/mo
Std dev
7.12
Lead time
30 d
Service factor
2.05
Network cover
38 EA
  • Demand at Ranjangaon averages 10.2 EA/month (variable profile, std dev 7.1).
  • Lead time is 30 days from Alfa Laval India (OTIF 96.8%).
  • Equipment criticality A on Mixing - Slurry Line (downtime ₹380,181/hr) sets a 2.04 service factor.
  • 38 equivalent units are available at other plants and can be transferred in days, not weeks.
reduce
Criticality B
1050101224 · Bidadi

BELT NAT-15EIC | Habasit | Modular Conveyor Belt 15mm Pitch

Reduce safety stock for Habasit NAT-15EIC at Bidadi from 48 to 3 M. Demand at Bidadi averages 5.8 M/month (stable profile, std dev 0.4). Lead time is 50 days from Habasit Iakoka (OTIF 71.7%). An additional 121 equivalent units are available across other plants.

Safety stock
48 → 3
₹5.58 Lakh released
On hand
52 M
Avg demand
5.83/mo
Std dev
0.37
Lead time
50 d
Service factor
1.64
Network cover
121 M
  • Demand at Bidadi averages 5.8 M/month (stable profile, std dev 0.4).
  • Lead time is 50 days from Habasit Iakoka (OTIF 71.7%).
  • Equipment criticality B on Biscuit Line 2 - Cooling Conveyor (downtime ₹105,685/hr) sets a 1.64 service factor.
  • 121 equivalent units are available at other plants and can be transferred in days, not weeks.
reduce
Criticality B
1010101888 · Ranjangaon

CHAIN SS-880-TAB | Rexnord | Table Top Chain SS 88.9mm

Reduce safety stock for Rexnord SS-880-TAB at Ranjangaon from 7 to 3 M. Demand at Ranjangaon averages 6.5 M/month (stable profile, std dev 0.5). Lead time is 38 days from Rexnord India (OTIF 94.4%). An additional 4 equivalent units are available across other plants.

Safety stock
7 → 3
₹35,950 released
On hand
71 M
Avg demand
6.5/mo
Std dev
0.5
Lead time
38 d
Service factor
1.64
Network cover
4 M
  • Demand at Ranjangaon averages 6.5 M/month (stable profile, std dev 0.5).
  • Lead time is 38 days from Rexnord India (OTIF 94.4%).
  • Equipment criticality B on Packaging Line 3 - Infeed (downtime ₹117,552/hr) sets a 1.64 service factor.
  • 4 equivalent units are available at other plants and can be transferred in days, not weeks.
  • No goods movement for 31 months — carrying risk outweighs stock-out risk.
reduce
Criticality C
1040102406 · Hajipur

PUMP CM5-4-A | Grundfos | Centrifugal Pump 0.75kW SS Var-3

Reduce safety stock for Grundfos CM5-4-A at Hajipur from 9 to 3 EA. Demand at Hajipur averages 1.1 EA/month (lumpy profile, std dev 1.6). Lead time is 54 days from Grundfos Pumps India (OTIF 80.3%). An additional 6 equivalent units are available across other plants.

Safety stock
9 → 3
₹4.62 Lakh released
On hand
12 EA
Avg demand
1.08/mo
Std dev
1.55
Lead time
54 d
Service factor
1.28
Network cover
6 EA
  • Demand at Hajipur averages 1.1 EA/month (lumpy profile, std dev 1.6).
  • Lead time is 54 days from Grundfos Pumps India (OTIF 80.3%).
  • Equipment criticality C on CIP Skid - Supply Pump (downtime ₹21,006/hr) sets a 1.28 service factor.
  • 6 equivalent units are available at other plants and can be transferred in days, not weeks.
reduce
Criticality A
1010101557 · Ranjangaon

SENSOR WTB4-3P2161 | Sick | Photoelectric Proximity Sensor PNP

Reduce safety stock for Sick WTB4-3P2161 at Ranjangaon from 60 to 2 EA. Demand at Ranjangaon averages 7.4 EA/month (stable profile, std dev 0.5). Lead time is 16 days from Sick India (OTIF 78.8%). An additional 113 equivalent units are available across other plants.

Safety stock
60 → 2
₹4.34 Lakh released
On hand
82 EA
Avg demand
7.42/mo
Std dev
0.49
Lead time
16 d
Service factor
2.05
Network cover
113 EA
  • Demand at Ranjangaon averages 7.4 EA/month (stable profile, std dev 0.5).
  • Lead time is 16 days from Sick India (OTIF 78.8%).
  • Equipment criticality A on Packaging Line 1 - Reject Gate (downtime ₹320,445/hr) sets a 2.04 service factor.
  • 113 equivalent units are available at other plants and can be transferred in days, not weeks.
  • No goods movement for 24 months — carrying risk outweighs stock-out risk.
reduce
Criticality A
1020102335 · Chennai

PUMP CM3-4-A | Grundfos | Centrifugal Pump 0.75kW SS

Reduce safety stock for Grundfos CM3-4-A at Chennai from 17 to 2 EA. Demand at Chennai averages 2.2 EA/month (stable profile, std dev 0.4). Lead time is 43 days from Grundfos Pumps India (OTIF 66.7%). An additional 36 equivalent units are available across other plants.

Safety stock
17 → 2
₹5.13 Lakh released
On hand
19 EA
Avg demand
2.25/mo
Std dev
0.43
Lead time
43 d
Service factor
2.05
Network cover
36 EA
  • Demand at Chennai averages 2.2 EA/month (stable profile, std dev 0.4).
  • Lead time is 43 days from Grundfos Pumps India (OTIF 66.7%).
  • Equipment criticality A on CIP Skid - Supply Pump (downtime ₹209,884/hr) sets a 2.04 service factor.
  • 36 equivalent units are available at other plants and can be transferred in days, not weeks.